• Electrical compliance
PAT testing for commercial and industrial sites
In-service inspection and testing of electrical equipment on a risk-based frequency rather than a blanket annual sweep, with a real asset register and digital certification for every site.
at a glance
- There is no legal requirement to PAT test annually. The duty is to maintain equipment in a safe condition, and how you meet it is for you to justify.
- Class II double-insulated equipment has no earth to test and generally needs visual inspection rather than routine electrical testing.
- New equipment does not need testing before first use. A visual check for transit damage is sufficient.
- The governing guidance is the IET Code of Practice, which sets out a risk-based approach rather than fixed intervals.
- Formal visual inspection finds the majority of faults, which is why it is scheduled more often than the electrical test.
- A 110V tool on a construction site may need testing every three months; a monitor that never moves may need no electrical test at all.
What is PAT testing?
PAT testing is the routine inspection and testing of electrical equipment that plugs into a socket, to confirm it is still safe to use. Its formal name is in-service inspection and testing of electrical equipment, and it combines a visual inspection, which finds most faults, with electrical tests appropriate to the class of equipment.
It covers anything with a plug: hand tools, kettles, computers, extension leads, floor cleaners, kitchen equipment. Anything wired permanently into the installation is fixed wire testing instead, and produces an Electrical Installation Condition Report rather than an appliance record.
The part most buyers are never told is that the visual inspection does most of the work. Damaged flex, a cracked plug, scorch marks around pins, a lead taped up where it enters the body of a tool: these are what actually injure people, and they are found by looking rather than by an instrument. The electrical test matters, but scheduling it monthly on equipment that never moves is not safety, it is invoicing.
What the tests actually check
- Visual inspection, of the plug, flex, body and any signs of damage, overheating or misuse
- Earth continuity, on Class I equipment that relies on an earth for safety
- Insulation resistance, confirming the insulation between live parts and earth or the casing
- Polarity and fuse rating, including on extension leads and adaptors
- Functional check that the item operates as intended
Class II equipment carries a double square symbol and has no earth. It is normally visually inspected rather than routinely tested, which is a meaningful cost difference across a large estate.
How often should equipment be tested?
These are indicative starting points from IET Code of Practice guidance, not legal intervals. The correct frequency for your site depends on the equipment, the environment and how it is actually handled, and it should be reviewed once you have failure data of your own.
| Environment and equipment | User check | Formal visual inspection | Combined inspection and test |
|---|---|---|---|
| Construction site equipment, 110V | Before each use | 1 month | 3 months |
| Industrial, including commercial kitchens | Before each use | 6 months | 6 to 12 months |
| Equipment used by the public, hand-held | By staff, daily | 6 months | 12 months |
| Schools and colleges | By staff | 4 months | 12 months |
| Hotels, hand-held and portable | By staff | 12 months | 24 months |
| Offices and shops, hand-held Class I | By user | 12 months | 24 months |
| Offices and shops, IT and stationary Class I | By user | 24 months | 48 months |
| Offices and shops, Class II equipment | By user | 24 months | Not normally required |
Two things follow from this table. Equipment in harsh environments needs attention far more often than an annual sweep provides, and equipment in benign ones needs it far less. A single annual frequency applied across a whole estate manages to be both unsafe and expensive at the same time.
How we run a PAT testing programme
We build the schedule from your asset register, not from a default. That takes slightly longer at the start and normally reduces both the volume and the cost of testing from the first year onwards.
A real asset register, not a pile of labels
Every item recorded with location, type, class, test date and next due date. On multi-site estates this is frequently more valuable than the testing itself, because most organisations do not actually know what portable equipment they own or where it is.
Risk-based frequencies, reviewed with you
We set intervals by equipment type and environment, then revise them once there is real failure data. If a category never fails, its interval should lengthen. If one department keeps damaging leads, that is a training issue rather than a testing issue.
Testing around your operations
Out of hours, overnight or department by department, so nothing is unplugged in the middle of a working day. Retail and hospitality are done outside trading hours as standard.
Honest failure reporting
Failed items are removed from service and reported with the reason, so you can decide between repair and replacement. You get a list, not a bin bag and an invoice.
User checks supported
We provide a short briefing and a checklist so your own staff can carry out the visual checks the Code of Practice encourages. It costs nothing and catches a real share of faults between formal visits.
Certification that survives an audit
Digital certificates per site, retained and reissued on request, formatted for insurers, auditors, principal contractors and health and safety managers.
What is included, step by step
Stage 01
Asset survey
Equipment located, counted, classified and tagged. Where a register already exists we validate it rather than starting again, because most are out of date rather than wrong.
Stage 02
Risk assessment
Frequencies set by equipment type and environment against IET Code of Practice guidance, and agreed with you rather than applied silently.
Stage 03
Visual inspection
Plug, flex, body and casing checked for damage, overheating, poor repairs and misuse. This is where most faults are found.
Stage 04
Electrical testing
Earth continuity on Class I, insulation resistance, polarity, fuse rating and a functional check, appropriate to the class of each item.
Stage 05
Failures handled
Failed items removed from service, labelled and reported with the reason, with repair or replacement quoted where you want it.
Stage 06
Certification and scheduling
Digital certification issued per site and the next due dates tracked, so the programme runs to a calendar rather than to whoever remembers.
Who needs PAT testing
Any employer with portable electrical equipment has a duty to maintain it. What changes between sectors is how often, and how much of the work should be visual rather than instrumented.
Construction and contracting
The shortest intervals of any environment. 110V tools take real punishment, leads get run over and connectors get wet, so formal visual inspection monthly and combined testing quarterly is normal. Principal contractors will usually ask to see the records before anyone starts.
Manufacturing and industrial
Hand-held equipment in dusty, hot or wet conditions ages far faster than an office estate. Six to twelve monthly testing is typical, and failure data usually justifies keeping it there rather than relaxing it.
Offices and professional services
The most over-tested environment in the country. Stationary IT equipment on a four-year cycle with periodic visual inspection is defensible, appropriate and much cheaper than an annual sweep of every monitor.
Hospitality, hotels and commercial kitchens
Kitchen equipment sits in heat, steam and grease and needs frequent attention. Guest-accessible equipment carries a different risk again, because it is used by people with no training and no reason to report a fault.
Schools, colleges and landlords
Equipment handled by people who did not buy it and will not be blamed for damaging it, which changes the failure profile. For landlords, appliance safety sits alongside the fixed installation duty and both tend to be asked about together.
PAT testing: common questions
No. There is no law that specifies a PAT testing interval, and the Health and Safety Executive has said plainly that the law does not require annual testing of all portable equipment. The duty comes from the Electricity at Work Regulations 1989 and the Provision and Use of Work Equipment Regulations 1998 to maintain equipment in a safe condition. How you meet that duty is for you to justify, which is what the risk-based approach is for.
Formally it is in-service inspection and testing of electrical equipment. PAT testing is the common name and the one everyone searches for, but the formal term is what should appear on certification and in tender responses. The governing document is the IET Code of Practice for In-service Inspection and Testing of Electrical Equipment.
No, and blanket annual testing of everything is usually money wasted. A 110V drill on a construction site may need a formal visual inspection monthly and a combined test every three months. A desktop monitor that has not moved in four years may need no electrical test at all, only periodic visual inspection. Moving to a risk-based schedule normally reduces both the cost and the volume of testing.
Class I equipment relies on an earth connection for safety, so it needs an earth continuity test as well as an insulation test. Class II equipment is double insulated, marked with a double square symbol, and has no earth to test. Class II items generally need visual inspection rather than routine electrical testing, which is why a proper asset register saves money: it stops you paying to test things that do not need it.
No. New equipment supplied with a manufacturer’s declaration of conformity does not need a formal test before first use. A visual check that it has not been damaged in transit is sufficient, and the item should then enter your inspection schedule at the appropriate interval for its type and environment. Testing new stock on arrival is a common and unnecessary cost.
Yes, and the IET Code of Practice actively encourages it. A user check is a visual look for damaged cables, cracked plugs, scorch marks, loose connections and taped repairs. It requires no instrument and no formal qualification, and it catches a large share of the faults that matter. We provide a short briefing and a simple checklist as part of a programme.
Neither is strictly required by law, but both are strongly advisable. A label tells a user at a glance when an item was last checked, and records are the evidence you rely on if you ever have to demonstrate that you met your duty to maintain equipment. In practice insurers, auditors and principal contractors all expect to see them.
They are removed from service immediately and recorded with the reason for failure, so you get a list rather than a surprise. You then decide item by item whether to repair or replace. Where a failure points at something systemic, such as repeated damage to leads in one department, that is worth knowing and we flag it.
Why Smartec Energy
- NICEIC registered, with qualified engineers
- A maintained asset register you can actually use for procurement and insurance
- One provider across PAT, fixed wire testing and emergency lighting, on a single renewal calendar
- Risk-based schedules built from your assets, not a default annual sweep
- Testing scheduled outside operating hours as standard
- Part of the Smartec Group, delivering building services on large commercial estates for over a decade
We would rather test less and explain why than sell you an annual sweep of everything. The second is easier to invoice and harder to defend.
Related pages
Commercial solar funding: PPA,hire purchase compared
The three ways to pay for a commercial solar system, with worked examples and tax position for each
Electrical compliance and EICR testing
Fixed wire testing, PAT testing and emergency lighting. Most renewable projects surface remedial work on the existing installation.
Commercial battery storage systems
Store the generation you cannot use as it is produced, sized from a full year of real data.
Get a PAT testing programme that fits
Send an approximate asset count and the type of site. We will propose a risk-based schedule rather than defaulting everything to annual, which is normally cheaper as well as more defensible.
No obligation, and no site visit needed to get started.