Home » Battery Storage
• Renewables
Commercial battery storage systems
Store the generation you cannot use as it is produced, cut what you pay during expensive periods, and add resilience where an outage would be costly. Designed and sized from your own consumption data rather than from a rule of thumb.
at a glance
- Battery storage holds surplus solar generation for use after dark, so more of what you generate is used on site rather than exported at a fraction of its value.
- A lithium-ion battery returns roughly 85 to 90 percent of the energy put into it, so there is a round-trip loss on every cycle.
- Storage that can export needs a G99 application to your Distribution Network Operator, the same as generation.
- Commercial systems should be sized from half-hourly consumption data, and ideally a full year of real generation data, not from the size of the solar array.
- Typical commercial battery life is ten to fifteen years, shorter than the twenty-five year performance warranty on solar panels.
- Fire safety and siting are designed in from the start, with reference to National Fire Chiefs Council guidance, not added at the end.
What is commercial battery storage?
Commercial battery storage is a system that stores electricity on your site so you can use it at a different time from when it was generated or bought. In practice it does two jobs: it holds solar generation you cannot consume during the day for use in the evening, and it lets you buy grid electricity during cheap periods to use during expensive ones.
The commercial case is different from the domestic one. A home battery is mostly about avoiding a high import rate in the evening. On a commercial site there are usually three separate savings running at once: displacing expensive imported units, reducing consumption during high distribution charge periods, and in some cases earning revenue by making capacity available to the grid.
Which of those matters most depends entirely on your consumption shape and your supply contract. A cold store that runs flat around the clock has a very different case from an office that peaks between nine and five, and a site already exporting half its solar generation has a different case again. That is why we start with half-hourly data rather than with a product.
The three ways a battery earns
- Self-consumption: storing solar you would otherwise export at a low rate, then using it at your full import rate
- Time shifting: charging when electricity and distribution charges are cheap, discharging when they are not
- Grid services: making capacity available to the network operator, where the site and the connection support it
Most commercial projects are justified on the first two. Grid services revenue is real but market-dependent, and we will not build a business case on it unless your site genuinely suits it.
How we size and specify a battery
We size from data, not from the solar array. The single most common fault in commercial battery projects is a system specified as a percentage of the generation rather than against what the site actually exports and when it actually draws.
Start with half-hourly data
Twelve months of half-hourly meter data shows exactly when you draw, how much, and at what cost. Where solar is already installed, generation data on top of that shows how much you currently export and could instead store. Without both, any sizing is guesswork dressed up as a proposal.
Size for the economics, not the roof
There is a point beyond which extra capacity captures units so rarely that it never repays. We model where that point sits for your site and recommend stopping there, even when a larger system would be an easier sale.
Design the fire strategy first
Siting, separation from buildings and escape routes, ventilation, thermal management and detection are settled before equipment is selected. On constrained sites this determines what is possible, and it is far cheaper to discover that at design stage.
Grid application early
A G99 application goes to your Distribution Network Operator as soon as the design supports it. Where the network is constrained, an export limit may be a condition of connection, which changes whether grid services are worth pursuing.
Specify backup deliberately or not at all
Standard grid-tied systems shut down in an outage. If you need the site to keep running, that requires an islanding-capable inverter and a defined set of essential circuits, designed in from the start.
Plan for replacement
Battery life is shorter than panel life. We set out expected replacement timing and cost at proposal stage so it appears in your numbers rather than surprising you in year twelve.
What is included, step by step
Stage 01
Data review
Half-hourly consumption and, where available, generation data analysed to establish what a battery could actually capture and what it would be worth.
Stage 02
Siting and fire strategy
Location, separation distances, ventilation and detection assessed against National Fire Chiefs Council guidance before any equipment is selected.
Stage 03
Sizing and design
Capacity and power rating specified against the economics, with inverter selection, integration with existing solar and any backup requirement settled.
Stage 04
Grid application
G99 submitted to your Distribution Network Operator, including any export limitation the network requires as a condition of connection.
Stage 05
Installation and commissioning
Installation to BS 7671 by qualified engineers, with testing, commissioning and handover documentation issued digitally.
Stage 06
Monitoring and maintenance
Live monitoring of state of charge, cycles and throughput, with servicing and fault response under an operation and maintenance package.
Which sites suit battery storage
Storage suits sites that already export significant solar, sites with a sharp difference between cheap and expensive periods, and sites where an outage carries a real cost.
Sites already exporting solar
If you are exporting a meaningful share of what you generate, you are selling units at a few pence that you could be using at your full import rate. That gap is the clearest case for storage, and it is measurable from existing generation data rather than modelled.
Cold storage and continuous process
Round-the-clock demand means stored energy is always used rather than sitting idle, and refrigeration loads respond well to shifting consumption away from expensive periods.
Manufacturing with peaky demand
Sites with short, sharp demand spikes from starting plant can use storage to shave those peaks, which can reduce capacity charges and in some cases avoid a supply upgrade.
Sites where an outage is expensive
Data and communications facilities, cold storage, care settings and anywhere a process cannot simply stop. Backup capability has to be designed in deliberately, but for these sites it can be the main reason to install.
Multi-site portfolios with flexible load
Where several sites can be operated together, aggregate capacity may open grid services that no single site could access alone.
Commercial battery storage: common questions
No, but it is usually the better order. A battery earns its money in two ways: storing your own generation for use later, and buying grid electricity when it is cheap to use when it is expensive. The second works without solar. The first does not, and it is normally the larger saving on a commercial site, which is why we recommend installing solar first and sizing storage against a full year of real generation data.
From half-hourly consumption data and, where solar is already installed, a full year of generation data. The number that matters is how much electricity you currently export or draw during expensive periods, because that is what a battery can capture. Sizing from roof area or from the size of the solar system rather than from the data is the most common way commercial batteries end up too large.
Typically ten to fifteen years, which is shorter than the twenty-five year performance warranty on solar panels. Batteries are usually warranted on throughput or cycle count rather than time alone, so a system cycled once a day will age differently from one cycled three times a day. Plan for replacement inside the life of the solar array.
When it is full, surplus generation is exported to the grid as it would be without a battery, just less often. When it approaches empty the system stops discharging at a set floor, usually around twenty percent, because taking a lithium battery to zero shortens its life considerably. The site simply draws from the grid again.
Yes. Every charge and discharge cycle loses energy, and a lithium-ion system typically returns around eighty-five to ninety percent of what you put in. That round-trip loss is why a battery should never be sized to catch every last exported unit: beyond a certain point you are paying for capacity that loses more than it saves.
Only if it is specified for it. Standard grid-tied battery systems shut down during an outage for safety reasons, so the site goes dark like everyone else. Backup capability needs an islanding-capable inverter and a defined set of essential circuits, which adds cost and needs designing in from the start rather than added later.
Yes. Storage capable of exporting to the network needs a G99 application to your Distribution Network Operator, in the same way generation does. Where the local network is constrained the connection may be granted with an export limit, which affects whether grid-services revenue is worth pursuing.
Yes, and they are the part of a battery project most often underestimated. Siting, separation distances from buildings and escape routes, ventilation, thermal management and fire detection all need to be designed in, with reference to National Fire Chiefs Council guidance. On constrained sites this frequently determines where the battery can go, and occasionally whether the project is viable at all.
Related pages
Commercial solar funding: PPA,hire purchase compared
The three ways to pay for a commercial solar system, with worked examples and tax position for each
Electrical compliance and EICR testing
Fixed wire testing, PAT testing and emergency lighting. Most renewable projects surface remedial work on the existing installation.
Commercial battery storage systems
Store the generation you cannot use as it is produced, sized from a full year of real data.
Find out whether storage stacks up on your site
Send twelve months of half-hourly data, or just a recent bill and details of any existing solar. We will tell you what a battery could realistically capture and whether it repays, before anyone quotes you for equipment.
No obligation, and no site visit needed to get started.